Phase 4 — Islands

Non-normative. Part of the implementation plan.

Goal: uniquely owned closed mutable graphs that move between tasks in O(1), and irreversible freezing into shareable immutable graphs.

Exit criterion: a cyclic graph moves between tasks with no deep copy and no shared mutation (island-pipeline reference program).

Spec inputs: spec 03 §12–15, 04 §13; RFC 0001 island sections move to Accepted.

Blocking questions: none recorded; log new ones before starting.

Invariants

  • iref<T> points only inside its own island and is never dereferenced without access to the owning island;
  • an island has no edges into foreign mutable memory;
  • after transfer the sender holds nothing that reaches the island;
  • a Frozen<T> never yields a mutable reference in safe code;
  • reference counts change only through explicit arc.clone / arc.release.

Tasks

ID Status Task Depends Output Done when
P4-1 todo Contract tables: island.create, island.alloc, island.freeze, iref access, arc.clone, arc.release — spec 07 appendix all spec 07 §4 fields present
P4-2 todo Island allocator in the interpreter (private regions, O(1) transfer) P4-1 src/interp/memory.zig transfer cost independent of graph size (unit benchmark with fixed bound)
P4-3 todo iref verifier and closure checks P4-1 src/verifier/island.zig E2110, E2111 accept/reject
P4-4 todo Island transfer through channels and task spawn; sender invalidation P4-3 verifier + interpreter sender use after send rejected (E2001)
P4-5 todo Freeze and Frozen<T>; Share/Send derivation P4-3 verifier + interpreter concurrent reads of frozen graph accepted; mutable access rejected
P4-6 todo Arc<T> for Share values P4-5 verifier + interpreter Arc of non-Share rejected (E4002); count changes visible in trace
P4-7 todo Reference program: island-pipeline P4-4, P4-5 tests/programs/island-pipeline/ passes under all P3 stress modes
P4-8 todo Phase exit review all plan status, RFC 0001 exit criterion passes; RFC 0001 fully Accepted

Conformance tests to add

Negative corpus entry owned by this phase: island internal reference escape. Plus E2111, freeze-then-mutate, Arc of non-Share.