plan: Phase 6A brought forward, P4/P5 paused; M and C become dev material

Owner decision after the native smoke: a minimal .aji frontend over the
frozen Phase 0-3 semantics (removes SSA, block parameters, CFG, feature
header; keeps every semantically significant action explicit), with
quantitative targets; quick reference and generic diagnostics in
parallel; new harder held-out benchmark; four conditions Rust, Zig,
Aji/AIR, Aji/source. Protocol: seen held-out tasks become dev material.
This commit is contained in:
dev committed 2026-10-05 10:09:53 +03:00
1 parent 5b7ecf9ffd
commit 80f5143c0e
4 files changed
+48 -3

No files matched your search

+1 -1
View File
@@ -209,7 +209,7 @@ test
## dev
Visible to Aji developers.
Visible to Aji developers. A held-out task whose results have been seen and used to choose a design direction becomes dev material from then on (for example, the two native-smoke tasks after 2026-10-05). It may serve for engineering regression, never as evidence for that design.
Used for: